| 1 |
Request for quote (RFQ). |
Fill in RFQ form and provide product design (2D/3D) for Magic to provide a quote. |
Engineering studies RFQ and provides quotes based on volume. |
1-2 weeks. |
| 2 |
Project go-ahead. |
Approves Magic's quote. |
Project kick-off. |
|
| 3 |
Update design & specs. |
Send latest CAD drawings, design notes, and specifications. |
|
3D (igs/stp)/ 2D (dxf/dwg) drawings for casting, machining and finishing are preferred. |
| 4 |
Tooling design. |
Provides tooling design guidance or transfers existing tooling. |
Design new tooling or modify existing tooling. Provide new tool design drawings for approval. |
1 week. |
| 5 |
Build/modify tooling. |
Reviews and approves tooling design. |
Build or modify tooling. |
New tooling: 30-60 days. Modification of existing tooling: 3-15 days. |
| 6 |
First sample production. |
Examines first production sample from Magic to determine if any modifications are needed (e.g., minor sizing adjustments). |
Changes tooling based on customer feedback. |
3-15 days. |
| 7 |
First batch production. |
Examines first production batch and approves production readiness. |
|
2-3 weeks. |
| 8 |
Production |
Places order and schedules production. |
|
|